This open house was active from Aug. 13-29, 2021. Information on this website may no longer be current. Email us for more information.

 

Project dates are estimates and subject to change.

 
  • Second open house

    Aug. 13-29, 2021

    You are here.

  • Project design

    Continues through February 2022
  • Right-of-way acquisition process

    Continues through February 2022
  • Construction: Stage 1

    Spring 2022 (2 months)

    Widen Farmington Road north of intersection. Farmington Road will remain open during construction.

    View pdf

  • Construction: Stage 2

    Spring-Summer (3 months)

    River Road will be closed south of the intersection while the lower part of the roundabout is built.

    Traffic will be detoured to Scholls Ferry Road and Hillsboro Highway (OR-219). Traffic must be detoured to roads with similar road classifications.

    View pdf

     

  • Construction: Stage 3

    Summer-Fall 2022 (2 months)

    The center of the roundabout will be built. Traffic will be rerouted:

    • Eastbound traffic on Farmington Road will be directed through the roundabout or will be able to turn south on River Road 

    • Westbound traffic on Farmington Road will be able to head north on River Road 

    • Northbound traffic on River Road will be must head east on Farmington Road 

    • Southbound traffic on River Road will be must head west on Farmington Road 

    View pdf

  • Construction: Stage 4

    Fall 2022 (2 months)

    River Road will be closed north of the intersection while the final portion of the roundabout is built. Access to the Farmington Paddle Launch will be maintained from the north.

    Traffic will be detoured to Hillsboro Highway (OR-219) and Minter Bridge Road. Traffic must be detoured to roads with similar road classifications.